Action Date | Action Description |
---|---|
Jun 23, 2010 | Assent Application Received |
Jun 24, 2010 | Administrative Review for Completeness |
Jun 24, 2010 | Team Review for Completeness |
Jun 24, 2010 | Team Review for Completeness |
Jun 24, 2010 | Application Accepted |
Jul 16, 2010 | Plans Received |
Jul 26, 2010 | HPHC Historical Preservation No Effect |
Jul 28, 2010 | 30 day Public Notice Issued |
Aug 28, 2010 | Public Notice End Date |
Aug 31, 2010 | Public Notice End Date Extension Granted |
Sep 21, 2010 | Dock/1.1.6 Review approval |
Sep 24, 2010 | Correspondence Received |
Sep 27, 2010 | Biologist Report |
Sep 27, 2010 | Engineering Report |
Oct 01, 2010 | Typist for Processing |
Oct 01, 2010 | Category A* (Docks) |
Oct 01, 2010 | Permit Approved |
Oct 04, 2010 | Executive Sign Off |
Oct 04, 2010 | Sent to Photo Copy |
Oct 06, 2010 | Land Evidence Date |
Oct 19, 2010 | US Army Corp of Engineers Permit Date |