Action Date | Action Description |
---|---|
Jul 01, 2010 | Assent Application Received |
Jul 02, 2010 | Administrative Review for Completeness |
Jul 02, 2010 | Team Review for Completeness |
Jul 06, 2010 | Team Review for Completeness |
Jul 21, 2010 | Deficient Application - Owner Notification Sent |
Jul 30, 2010 | Deficiency Response Received |
Jul 30, 2010 | Team Review for Completeness |
Jul 30, 2010 | Team Review for Completeness |
Jul 30, 2010 | Application Accepted |
Aug 12, 2010 | HPHC Historical Preservation No Effect |
Sep 08, 2010 | Biologist Report |
Sep 08, 2010 | Engineering Report |
Sep 13, 2010 | Typist for Processing |
Sep 13, 2010 | Permit Approved |
Sep 15, 2010 | Executive Sign Off |
Sep 15, 2010 | Sent to Photo Copy |
Oct 01, 2010 | Land Evidence Date |