Action Date | Action Description |
---|---|
Jul 07, 2010 | Assent Application Received |
Jul 09, 2010 | Administrative Review for Completeness |
Jul 16, 2010 | Team Review for Completeness |
Jul 16, 2010 | Team Review for Completeness |
Jul 16, 2010 | Application Accepted |
Jul 23, 2010 | Engineering Report |
Jul 23, 2010 | Biologist Report |
Jul 26, 2010 | HPHC Historical Preservation No Effect |
Jul 27, 2010 | Typist for Processing |
Jul 27, 2010 | Executive Sign Off |
Jul 27, 2010 | Sent to Photo Copy |
Jul 27, 2010 | Permit Approved |
Sep 27, 2011 | Modification Request |
Sep 28, 2011 | Administrative Review for Completeness |
Sep 28, 2011 | Team Review for Completeness |
Sep 28, 2011 | Engineering Report |
Oct 06, 2011 | Typist for Processing |
Oct 06, 2011 | Modification Approved |
Oct 11, 2011 | Executive Sign Off |
Oct 12, 2011 | Sent to Photo Copy |
Nov 25, 2011 | Modification Request |
Dec 02, 2011 | Administrative Review for Completeness |
Dec 02, 2011 | Team Review for Completeness |
Dec 07, 2011 | Modification Approved |
Dec 09, 2011 | Typist for Processing |
Dec 12, 2011 | Executive Sign Off |
Dec 12, 2011 | Sent to Photo Copy |