Action Date | Action Description |
---|---|
Aug 20, 2010 | Assent Application Received |
Aug 23, 2010 | Administrative Review for Completeness |
Aug 27, 2010 | Team Review for Completeness |
Aug 27, 2010 | Team Review for Completeness |
Aug 27, 2010 | Application Accepted |
Aug 27, 2010 | Category B assigned |
Aug 31, 2010 | Category A assigned |
Aug 31, 2010 | 30 day Public Notice Issued |
Sep 16, 2010 | HPHC Historical Preservation No Effect |
Sep 30, 2010 | Public Notice End Date |
Oct 22, 2010 | US Army Corp of Engineers Permit Date |
Nov 15, 2010 | Dock Meeting -- Approval |
Nov 15, 2010 | Biologist Report |
Nov 15, 2010 | Engineering Report |
Nov 15, 2010 | Dock/1.1.6 Review approval |
Dec 03, 2010 | Typist for Processing |
Dec 03, 2010 | Executive Sign Off |
Dec 03, 2010 | Permit Approved |
Dec 17, 2010 | Land Evidence Date |