Action Date | Action Description |
---|---|
Sep 07, 2010 | Assent Application Received |
Sep 07, 2010 | Administrative Review for Completeness |
Sep 07, 2010 | Team Review for Completeness |
Sep 07, 2010 | Team Review for Completeness |
Sep 07, 2010 | Application Accepted |
Sep 09, 2010 | Additional Information Received |
Sep 14, 2010 | Biologist Report |
Sep 15, 2010 | Engineering Report |
Sep 16, 2010 | Typist for Processing |
Sep 16, 2010 | HPHC Historical Preservation No Effect |
Sep 16, 2010 | Permit Approved |
Sep 20, 2010 | Executive Sign Off |
Sep 20, 2010 | Sent to Photo Copy |
Sep 29, 2010 | Land Evidence Date |