Action Date | Action Description |
---|---|
Sep 15, 2010 | Assent Application Received |
Sep 17, 2010 | Administrative Review for Completeness |
Sep 21, 2010 | Team Review for Completeness |
Sep 21, 2010 | Team Review for Completeness |
Sep 21, 2010 | Application Accepted |
Sep 21, 2010 | Category A* (Docks) |
Sep 22, 2010 | Correspondence Received |
Sep 27, 2010 | Additional Information Received |
Sep 28, 2010 | 30 day Public Notice Issued |
Oct 07, 2010 | HPHC Historical Preservation No Effect |
Oct 25, 2010 | US Army Corp of Engineers Permit Date |
Oct 28, 2010 | Public Notice End Date |
Nov 15, 2010 | Dock Meeting -- Approval |
Nov 16, 2010 | Engineering Report |
Nov 16, 2010 | Biologist Report |
Nov 22, 2010 | Permit Approved |
Nov 22, 2010 | Typist for Processing |
Nov 23, 2010 | Executive Sign Off |
Nov 23, 2010 | Sent to Photo Copy |
Dec 01, 2010 | Land Evidence Date |