Action Date | Action Description |
---|---|
Sep 15, 2010 | Assent Application Received |
Sep 17, 2010 | Administrative Review for Completeness |
Sep 27, 2010 | Team Review for Completeness |
Sep 27, 2010 | Team Review for Completeness |
Sep 27, 2010 | Application Accepted |
Nov 15, 2010 | 30 day Public Notice Issued |
Nov 16, 2010 | HPHC Historical Preservation No Effect |
Dec 15, 2010 | Objections/Comments Received |
Dec 15, 2010 | Public Notice End Date |
Jan 18, 2011 | Objections/Comments Received |
Mar 17, 2011 | Additional Information Received |
Mar 30, 2011 | Withdrawal Request Received |
Mar 30, 2011 | US Army Corps of Engineers Approval Received |
Apr 06, 2011 | Dock Meeting -- Approval |
Apr 07, 2011 | Biologist Report |
Apr 07, 2011 | Engineering Report |
Apr 11, 2011 | Executive Sign Off |
Apr 11, 2011 | Sent to Photo Copy |
Apr 12, 2011 | Permit Approved |
Apr 12, 2011 | Typist for Processing |
May 06, 2011 | Land Evidence Date |
Sep 19, 2011 | Commencement of Work Notice received |