Action Date | Action Description |
---|---|
Oct 01, 2010 | Team Review for Completeness |
Oct 01, 2010 | Assent Application Received |
Oct 01, 2010 | Administrative Review for Completeness |
Oct 06, 2010 | Team Review for Completeness |
Oct 06, 2010 | Application Accepted |
Oct 08, 2010 | Engineering Report |
Oct 15, 2010 | Permit Approved |
Oct 18, 2010 | Typist for Processing |
Oct 18, 2010 | Executive Sign Off |
Oct 18, 2010 | Sent to Photo Copy |
Oct 20, 2010 | Land Evidence Date |
Nov 18, 2010 | Modification Request |
Nov 22, 2010 | Administrative Review for Completeness |
Jan 25, 2011 | Typist for Processing |
Jan 25, 2011 | Executive Sign Off |
Jan 25, 2011 | Sent to Photo Copy |
Jan 25, 2011 | Modification Approved |
Jan 31, 2011 | Land Evidence Date |