Action Date | Action Description |
---|---|
Oct 01, 2010 | Assent Application Received |
Oct 01, 2010 | Administrative Review for Completeness |
Oct 13, 2010 | Team Review for Completeness |
Oct 13, 2010 | Team Review for Completeness |
Oct 13, 2010 | Application Accepted |
Oct 20, 2010 | HPHC Historical Preservation No Effect |
Nov 15, 2010 | 30 day Public Notice Issued |
Dec 15, 2010 | Public Notice End Date |
Feb 18, 2011 | Additional Information Received |
Mar 01, 2011 | US Army Corps of Engineers Approval Received |
Mar 11, 2011 | Additional Information Received |
Mar 18, 2011 | Correspondence Received |
Mar 18, 2011 | Correspondence Received |
Apr 07, 2011 | Biologist Report |
Apr 07, 2011 | Engineering Report |
Apr 12, 2011 | Typist for Processing |
Apr 12, 2011 | Executive Sign Off |
Apr 12, 2011 | Sent to Photo Copy |
Apr 12, 2011 | Permit Approved |
Apr 29, 2011 | Land Evidence Date |
Jun 06, 2011 | Commencement of Work Notice received |