Action Date | Action Description |
---|---|
Oct 04, 2010 | Assent Application Received |
Oct 05, 2010 | Administrative Review for Completeness |
Oct 05, 2010 | Team Review for Completeness |
Oct 05, 2010 | Team Review for Completeness |
Oct 05, 2010 | Application Accepted |
Oct 06, 2010 | Biologist Report |
Oct 06, 2010 | Engineering Report |
Oct 07, 2010 | Typist for Processing |
Oct 07, 2010 | Permit Approved |
Oct 08, 2010 | Executive Sign Off |
Oct 08, 2010 | Sent to Photo Copy |
Oct 12, 2010 | Land Evidence Date |
Nov 16, 2010 | HPHC Historical Preservation Comments/Concerns |
May 06, 2011 | Modification Request |
Jul 22, 2013 | Modification Request |
Aug 02, 2013 | Team Review for Completeness |
Aug 02, 2013 | Administrative Review for Completeness |
Aug 28, 2013 | Additional Information Received |
Sep 03, 2013 | Biologist Report |
Sep 05, 2013 | Typist for Processing |
Sep 05, 2013 | Executive Sign Off |
Sep 05, 2013 | Sent to Photo Copy |
Sep 05, 2013 | Modification Approved |
Sep 18, 2013 | HPHC Historical Preservation No Effect |
Sep 24, 2013 | Land Evidence Date |