Action Date | Action Description |
---|---|
Oct 20, 2010 | Assent Application Received |
Oct 25, 2010 | Administrative Review for Completeness |
Oct 25, 2010 | Team Review for Completeness |
Oct 25, 2010 | Team Review for Completeness |
Oct 25, 2010 | Application Accepted |
Oct 29, 2010 | Biologist Report |
Oct 29, 2010 | Engineering Report |
Nov 05, 2010 | Typist for Processing |
Nov 05, 2010 | Permit Approved |
Nov 08, 2010 | Executive Sign Off |
Nov 08, 2010 | Sent to Photo Copy |
Nov 09, 2010 | HPHC Historical Preservation No Effect |