Action Date | Action Description |
---|---|
Oct 27, 2010 | Freshwater Wetland - Preliminary Determination |
Oct 27, 2010 | Administrative Review for Completeness |
Nov 30, 2010 | Team Review for Completeness |
Dec 01, 2010 | Team Review for Completeness |
Dec 03, 2010 | Application Accepted |
Dec 03, 2010 | Biologist Report |
Dec 03, 2010 | Typist for Processing |
Dec 03, 2010 | Permit Approved |
Dec 07, 2010 | Executive Sign Off |
Dec 07, 2010 | Sent to Photo Copy |
Jul 29, 2011 | Freshwater Wetland - Permit Modification Request |
Aug 01, 2011 | Administrative Review for Completeness |
Aug 11, 2011 | Modification Approved |
Aug 15, 2011 | Land Evidence Date |
Aug 15, 2011 | Typist for Processing |
Aug 15, 2011 | Executive Sign Off |
Aug 15, 2011 | Sent to Photo Copy |