Action Date | Action Description |
---|---|
Nov 03, 2010 | Assent Application Received |
Nov 03, 2010 | Administrative Review for Completeness |
Nov 18, 2010 | Correspondence Mailed/Faxed/E-mailed |
Dec 14, 2010 | 30 day Public Notice Issued |
Dec 14, 2010 | Team Review for Completeness |
Dec 14, 2010 | Team Review for Completeness |
Dec 14, 2010 | Application Accepted |
Dec 14, 2010 | Category B assigned |
Jan 10, 2011 | Objections/Comments Received |
Jan 11, 2011 | HPHC Historical Preservation No Effect |
Jan 11, 2011 | Correspondence Received |
Jan 13, 2011 | Correspondence Received |
Jan 14, 2011 | Public Notice End Date |
Jan 14, 2011 | Biologist Report |
Jan 14, 2011 | Engineering Report |
Jan 18, 2011 | Correspondence Received |
Jan 20, 2011 | Supervisor Biologist SignOff |
Jan 20, 2011 | Supervisor Engineer SignOff |
Jan 21, 2011 | Executive Signoff of Staff Reports |
Feb 08, 2011 | Semi-Monthly Meeting Held |
Feb 08, 2011 | Council Approval Granted |
Feb 14, 2011 | Stipulation Package from Biologist |
Feb 14, 2011 | Stipulation Package by Engineer |
Apr 13, 2011 | Legal Response/Decision |
Apr 13, 2011 | Typist for Processing |
Apr 13, 2011 | Permit Approved |
Apr 20, 2011 | Executive Sign Off |
Apr 21, 2011 | Sent to Photo Copy |
Apr 28, 2011 | Land Evidence Date |
Feb 28, 2013 | Additional Information Received |
Mar 05, 2013 | Letter of Authorization |