Action Date | Action Description |
---|---|
Nov 23, 2010 | Assent Application Received |
Nov 24, 2010 | Administrative Review for Completeness |
Nov 29, 2010 | Team Review for Completeness |
Nov 29, 2010 | Team Review for Completeness |
Nov 29, 2010 | Application Accepted |
Dec 08, 2010 | HPHC Historical Preservation No Effect |
Dec 15, 2010 | 30 day Public Notice Issued |
Jan 31, 2011 | Public Notice End Date Extension Granted |
Feb 01, 2011 | Biologist Report |
Feb 01, 2011 | Engineering Report |
Feb 03, 2011 | Supervisor Engineer SignOff |
Feb 03, 2011 | Supervisor Biologist SignOff |
Feb 03, 2011 | Executive Signoff of Staff Reports |
Feb 08, 2011 | Correspondence Received |
Mar 02, 2011 | Ready to Schedule Semi-Monthly Meeting |
Mar 02, 2011 | Mail Agenda Notice |
Mar 08, 2011 | Council Approval Granted |
Mar 08, 2011 | Semi-Monthly Meeting Date Scheduled |
Mar 08, 2011 | Semi-Monthly Meeting Held |
Apr 13, 2011 | Legal Response/Decision |
Apr 18, 2011 | Permit Approved |
Apr 18, 2011 | Typist for Processing |
Apr 18, 2011 | Stipulation Package from Biologist |
Apr 18, 2011 | Stipulation Package by Engineer |
Apr 21, 2011 | Executive Sign Off |
Apr 21, 2011 | Sent to Photo Copy |
Jun 23, 2011 | Land Evidence Date |