Action Date | Action Description |
---|---|
Nov 23, 2010 | Assent Application Received |
Nov 26, 2010 | Administrative Review for Completeness |
Nov 30, 2010 | Team Review for Completeness |
Nov 30, 2010 | Application Accepted |
Dec 06, 2010 | 30 day Public Notice Issued |
Dec 08, 2010 | HPHC Historical Preservation No Effect |
Jan 06, 2011 | Public Notice End Date |
Jan 13, 2011 | Objections/Comments Received |
Apr 08, 2011 | Objections/Comments Received |
Nov 23, 2012 | Additional Information Received |
Dec 13, 2012 | 30 day Public Notice Issued |
Jan 13, 2013 | Public Notice End Date |
Jan 14, 2013 | Dock/1.1.6 Review approval |
Jan 15, 2013 | Biologist Report |
Feb 04, 2013 | Permit Approved |
Feb 04, 2013 | Typist for Processing |
Feb 04, 2013 | Category A* (Docks) |
Feb 05, 2013 | Executive Sign Off |
Feb 05, 2013 | Sent to Photo Copy |
Feb 20, 2013 | US Army Corp of Engineers Permit Date |
Jun 24, 2015 | Land Evidence Date |
Sep 14, 2018 | Expiration of Assent/End of Tolling Legislation |
Oct 10, 2018 | Extension of Permit Request |
Nov 26, 2018 | Enforcement Compliance Inspection Required |
Nov 26, 2018 | Process Extension |
Nov 26, 2018 | Extension Approved |