Action Date | Action Description |
---|---|
Nov 29, 2010 | Assent Application Received |
Nov 30, 2010 | Administrative Review for Completeness |
Dec 09, 2010 | Team Review for Completeness |
Dec 09, 2010 | Team Review for Completeness |
Dec 09, 2010 | Application Accepted |
Dec 21, 2010 | Biologist Report |
Dec 21, 2010 | Engineering Report |
Dec 21, 2010 | Plans Received |
Dec 22, 2010 | Typist for Processing |
Dec 22, 2010 | Permit Approved |
Dec 28, 2010 | Executive Sign Off |
Dec 28, 2010 | Sent to Photo Copy |
Jan 03, 2011 | Land Evidence Date |
Feb 28, 2011 | Commencement of Work Notice received |