Action Date | Action Description |
---|---|
Dec 07, 2010 | Assent Application Received |
Dec 08, 2010 | Administrative Review for Completeness |
Dec 13, 2010 | Team Review for Completeness |
Dec 13, 2010 | Team Review for Completeness |
Dec 13, 2010 | Application Accepted |
Dec 17, 2010 | HPHC Historical Preservation No Effect |
Dec 29, 2010 | Additional Information Received |
Dec 29, 2010 | Correspondence Received |
Jan 25, 2011 | Additional Information Received |
Jan 27, 2011 | Additional Information Received |
Feb 03, 2011 | Typist for Processing |
Feb 03, 2011 | Biologist Report |
Feb 03, 2011 | Engineering Report |
Feb 03, 2011 | Permit Approved |
Feb 04, 2011 | Executive Sign Off |
Feb 04, 2011 | Sent to Photo Copy |
Feb 08, 2011 | Land Evidence Date |
Aug 18, 2011 | Water Quality Certification |