Action Date | Action Description |
---|---|
Dec 13, 2010 | Assent Application Received |
Dec 13, 2010 | Administrative Review for Completeness |
Dec 13, 2010 | Team Review for Completeness |
Dec 13, 2010 | Team Review for Completeness |
Dec 13, 2010 | Application Accepted |
Dec 17, 2010 | HPHC Historical Preservation No Effect |
Dec 29, 2010 | Correspondence Received |
Dec 30, 2010 | 30 day Public Notice Issued |
Jan 30, 2011 | Public Notice End Date |
Feb 10, 2011 | Additional Information Received |
Feb 23, 2011 | Biologist Report |
Feb 28, 2011 | Engineering Report |
Mar 01, 2011 | Additional Information Received |
Mar 02, 2011 | Special Exception Public Hearing Notice mailed |
Mar 02, 2011 | Mail Agenda Notice |
Mar 04, 2011 | Executive Signoff of Staff Reports |
Apr 04, 2011 | US Army Corps of Engineers Approval Received |
Apr 12, 2011 | Semi-Monthly Meeting Held |
Apr 12, 2011 | Council Approval Granted |
Apr 12, 2011 | Semi-Monthly Meeting Date Scheduled |
Jun 07, 2011 | Legal Response/Decision |
Jun 15, 2011 | Typist for Processing |
Jun 15, 2011 | Permit Approved |
Jun 20, 2011 | Executive Sign Off |
Jun 20, 2011 | Sent to Photo Copy |
Jun 20, 2011 | Under Review/Decision |
Jun 20, 2011 | Stipulation Package from Biologist |
Jun 20, 2011 | Stipulation Package by Engineer |
Jun 28, 2011 | Land Evidence Date |
Oct 06, 2011 | Commencement of Work Notice received |