Action Date | Action Description |
---|---|
Dec 16, 2010 | Assent Application Received |
Dec 17, 2010 | Administrative Review for Completeness |
Dec 17, 2010 | Team Review for Completeness |
Dec 17, 2010 | Team Review for Completeness |
Dec 17, 2010 | Typist for Processing |
Dec 17, 2010 | Executive Sign Off |
Dec 17, 2010 | Sent to Photo Copy |
Dec 17, 2010 | Permit Approved |
Jan 04, 2011 | Land Evidence Date |