Action Date | Action Description |
---|---|
Ready to Schedule Semi-Monthly Meeting | |
Dec 24, 2010 | Assent Application Received |
Dec 29, 2010 | Administrative Review for Completeness |
Feb 21, 2011 | Team Review for Completeness |
Feb 21, 2011 | Team Review for Completeness |
Feb 21, 2011 | Application Accepted |
Feb 28, 2011 | HPHC Historical Preservation No Effect |
Sep 16, 2011 | Biologist Report |
Sep 16, 2011 | Engineering Report |
Sep 19, 2011 | Supervisor Biologist SignOff |
Sep 19, 2011 | Supervisor Engineer SignOff |
Sep 23, 2011 | Executive Signoff of Staff Reports |
Apr 11, 2013 | Ready to Schedule Semi-Monthly Meeting |
Apr 11, 2013 | Mail Agenda Notice |
Apr 15, 2013 | Continuance Requested |
Apr 15, 2013 | Management Review |
Apr 15, 2013 | Continuance request by applicant granted by Director |
Apr 19, 2013 | Ready to Schedule Semi-Monthly Meeting |
Apr 19, 2013 | Mail Agenda Notice |
Jun 07, 2013 | Continued application |
Jun 11, 2013 | Semi-Monthly Meeting Date Scheduled |
Sep 10, 2013 | Ready to Schedule Semi-Monthly Meeting |
Sep 11, 2013 | Mail Agenda Notice |
Sep 16, 2013 | Continued application |