Action Date |
Action Description |
Jan 06, 2011 |
Assent Application Received |
Jan 07, 2011 |
Administrative Review for Completeness |
Jan 10, 2011 |
Team Review for Completeness |
Jan 10, 2011 |
Team Review for Completeness |
Jan 10, 2011 |
Application Accepted |
Jan 10, 2011 |
Category B assigned |
Jan 24, 2011 |
30 day Public Notice Issued |
Feb 14, 2011 |
Objections/Comments Received |
Feb 24, 2011 |
Public Notice End Date |
Mar 17, 2011 |
HPHC Historical Preservation Comments/Concerns |
May 04, 2011 |
Additional Information Received |
Jun 30, 2011 |
Additional Information Received |
Jul 07, 2011 |
30 day Public Notice Issued |
Aug 07, 2011 |
Public Notice End Date |
Aug 22, 2011 |
Correspondence Mailed/Faxed/E-mailed |
Sep 06, 2011 |
Objections/Comments Received |
Oct 03, 2011 |
Additional Information Received |
Oct 07, 2011 |
Additional Information Received |
Sep 19, 2012 |
Additional Information Received |
Oct 25, 2012 |
Correspondence Received |
Jan 23, 2013 |
Water Quality Certification |
Jan 31, 2013 |
Correspondence Received |
Feb 05, 2013 |
US Army Corps of Engineers Approval Received |
Feb 19, 2013 |
Biologist Report |
Feb 20, 2013 |
Supervisor Biologist SignOff |
Feb 20, 2013 |
Supervisor Engineer SignOff |
Feb 20, 2013 |
Executive Signoff of Staff Reports |
Feb 25, 2013 |
Ready to Schedule Semi-Monthly Meeting |
Feb 25, 2013 |
Mail Agenda Notice |
Mar 26, 2013 |
Council Approval Granted |
Mar 26, 2013 |
Semi-Monthly Meeting Date Scheduled |
Apr 04, 2013 |
Stipulation Package from Biologist |
Apr 04, 2013 |
Stipulation Package by Engineer |
Apr 05, 2013 |
Typist for Processing |
Apr 18, 2013 |
Additional Information Received |
Apr 18, 2013 |
Plans Received |
Apr 19, 2013 |
Correspondence Mailed/Faxed/E-mailed |
May 14, 2013 |
30 Day Appeal Notification to Owner |
May 14, 2013 |
Executive Sign Off |
May 14, 2013 |
Sent to Photo Copy |
May 14, 2013 |
Legal Response/Decision |
Jun 27, 2016 |
Extension Toll letter mailed |