Action Date | Action Description |
---|---|
Jan 19, 2011 | Assent Application Received |
Jan 19, 2011 | Administrative Review for Completeness |
Jan 20, 2011 | Team Review for Completeness |
Jan 20, 2011 | Team Review for Completeness |
Jan 20, 2011 | Plans Received |
Jan 20, 2011 | Application Accepted |
Jan 20, 2011 | Category A* (Docks) |
Jan 28, 2011 | HPHC Historical Preservation No Effect |
Feb 16, 2011 | Additional Information Received |
Feb 25, 2011 | Additional Information Received |
Mar 02, 2011 | Additional Information Received |
Mar 03, 2011 | 30 day Public Notice Issued |
Apr 03, 2011 | Public Notice End Date |
May 02, 2011 | US Army Corps of Engineers Approval Received |
May 17, 2011 | Typist for Processing |
May 17, 2011 | Biologist Report |
May 17, 2011 | Engineering Report |
May 17, 2011 | Permit Approved |
May 18, 2011 | Executive Sign Off |
May 18, 2011 | Sent to Photo Copy |
May 23, 2011 | Land Evidence Date |