Action Date | Action Description |
---|---|
Jan 21, 2011 | Federal Consistency Review Request |
Jan 24, 2011 | Administrative Review for Completeness |
Jan 24, 2011 | Team Review for Completeness |
Jan 24, 2011 | Application Accepted |
Mar 31, 2011 | Additional Information Requested from Applicant |
May 16, 2011 | Correspondence Received |
Sep 01, 2011 | HPHC Historical Preservation Comments/Concerns |
Sep 27, 2011 | Additional Information Requested from Applicant |
Dec 19, 2011 | HPHC Historical Preservation Comments/Concerns |
Apr 16, 2012 | Additional Information Received |
Aug 28, 2012 | Historical Preservation Conditional Approval |
Dec 21, 2012 | Correspondence Received |
Dec 21, 2012 | Correspondence Received |
Dec 24, 2012 | Correspondence Received |
Dec 27, 2012 | Correspondence Received |
Feb 19, 2013 | Mail Agenda Notice |
Feb 21, 2013 | Engineering Report |
Feb 28, 2013 | Ready to Schedule Semi-Monthly Meeting |
Mar 26, 2013 | Semi-Monthly Meeting Date Scheduled |
Mar 28, 2013 | Federal Consistency FMP Concurrence |