Action Date | Action Description |
---|---|
Feb 11, 2011 | Assent Application Received |
Feb 14, 2011 | Administrative Review for Completeness |
Feb 14, 2011 | Team Review for Completeness |
Feb 14, 2011 | Team Review for Completeness |
Feb 14, 2011 | Application Accepted |
Feb 15, 2011 | Additional Information Received |
Mar 17, 2011 | HPHC Historical Preservation No Effect |
Mar 23, 2011 | Additional Information Received |
Jul 01, 2011 | Additional Information Received |
Aug 18, 2011 | Additional Information Received |
Aug 18, 2011 | Biologist Report |
Aug 18, 2011 | Engineering Report |
Aug 23, 2011 | Typist for Processing |
Aug 23, 2011 | Permit Approved |
Aug 25, 2011 | Executive Sign Off |
Aug 25, 2011 | Sent to Photo Copy |
Aug 31, 2011 | Land Evidence Date |
Oct 24, 2011 | Commencement of Work Notice received |
Feb 08, 2012 | Modification Request |
Feb 08, 2012 | Administrative Review for Completeness |
Feb 09, 2012 | Team Review for Completeness |
Feb 09, 2012 | Team Review for Completeness |
Feb 15, 2012 | Biologist Report |
Feb 15, 2012 | Engineering Report |
Feb 17, 2012 | Typist for Processing |
Feb 17, 2012 | Executive Sign Off |
Feb 17, 2012 | Sent to Photo Copy |
Feb 17, 2012 | Modification Approved |
Feb 27, 2012 | Land Evidence Date |
Mar 06, 2012 | HPHC Historical Preservation No Effect |