Action Date | Action Description |
---|---|
Mar 07, 2011 | Assent Application Received |
Mar 08, 2011 | Administrative Review for Completeness |
Mar 08, 2011 | Team Review for Completeness |
Mar 08, 2011 | Application Accepted |
Mar 10, 2011 | 30 day Public Notice Issued |
Mar 17, 2011 | HPHC Historical Preservation No Effect |
Mar 28, 2011 | Public Notice End Date Extension Granted |
Apr 11, 2011 | Public Notice End Date |
Apr 11, 2011 | Objections/Comments Received |
Apr 11, 2011 | Objections/Comments Received |
May 02, 2011 | US Army Corps of Engineers Approval Received |
May 02, 2011 | Public Notice End Date Extension Granted |
May 04, 2011 | Objections/Comments Received |
May 23, 2011 | Engineering Report |
May 24, 2011 | Objections/Comments Received |
Jun 03, 2011 | Executive Signoff of Staff Reports |
Jun 08, 2011 | Ready to Schedule Semi-Monthly Meeting |
Jun 14, 2011 | Mail Agenda Notice |
Jun 28, 2011 | Council Approval Granted |
Jun 28, 2011 | Semi-Monthly Meeting Date Scheduled |
Jun 28, 2011 | Semi-Monthly Meeting Held |
Jul 12, 2011 | Legal Response/Decision |
Aug 17, 2011 | Under Review/Decision |
Aug 17, 2011 | Stipulation Package from Biologist |
Aug 17, 2011 | Stipulation Package by Engineer |
Sep 09, 2011 | Category B assigned |
Sep 09, 2011 | Typist for Processing |
Sep 09, 2011 | Permit Approved |
Sep 12, 2011 | Executive Sign Off |
Sep 12, 2011 | Sent to Photo Copy |
Sep 30, 2011 | Land Evidence Date |
Sep 30, 2011 | Commencement of Work Notice received |