Action Date | Action Description |
---|---|
Monitoring Report | |
Mar 09, 2011 | Assent Application Received |
Mar 10, 2011 | Administrative Review for Completeness |
Mar 29, 2011 | Team Review for Completeness |
Mar 29, 2011 | Team Review for Completeness |
Mar 29, 2011 | Application Accepted |
Apr 08, 2011 | HPHC Historical Preservation No Effect |
Apr 20, 2011 | 30 day Public Notice Issued |
May 20, 2011 | Public Notice End Date |
May 20, 2011 | Additional Information Received |
Jul 08, 2011 | Additional Information Received |
Jul 11, 2011 | Additional Information Received |
Jul 14, 2011 | Additional Information Received |
Jul 15, 2011 | Plans Received |
Jul 18, 2011 | Additional Information Received |
Jul 19, 2011 | Objections/Comments Received |
Jul 19, 2011 | Biologist Report |
Jul 19, 2011 | Engineering Report |
Jul 19, 2011 | Supervisor Biologist SignOff |
Jul 19, 2011 | Supervisor Engineer SignOff |
Jul 20, 2011 | Executive Signoff of Staff Reports |
Jul 20, 2011 | Ready to Schedule Semi-Monthly Meeting |
Jul 20, 2011 | Mail Agenda Notice |
Jul 26, 2011 | Council Approval Granted |
Jul 26, 2011 | Semi-Monthly Meeting Held |
Jul 26, 2011 | Semi-Monthly Meeting Date Scheduled |
Aug 04, 2011 | Plans Received |
Aug 04, 2011 | Legal Response/Decision |
Aug 18, 2011 | Land Evidence Date |
Aug 18, 2011 | Water Quality Certification |
Aug 18, 2011 | Stipulation Package from Biologist |
Aug 18, 2011 | Stipulation Package by Engineer |
Aug 19, 2011 | Typist for Processing |
Aug 19, 2011 | Executive Sign Off |
Aug 19, 2011 | Sent to Photo Copy |
Aug 19, 2011 | Permit Approved |
Aug 24, 2011 | Monitoring Report |
Aug 30, 2011 | Land Evidence Date |
Aug 31, 2011 | Commencement of Work Notice received |