Action Date | Action Description |
---|---|
Apr 11, 2011 | Assent Application Received |
Apr 11, 2011 | Administrative Review for Completeness |
Apr 12, 2011 | Team Review for Completeness |
Apr 12, 2011 | Application Accepted |
Apr 12, 2011 | Engineering Report |
Apr 14, 2011 | Typist for Processing |
Apr 14, 2011 | Permit Approved |
Apr 18, 2011 | Executive Sign Off |
Apr 18, 2011 | Sent to Photo Copy |
Apr 19, 2011 | HPHC Historical Preservation No Effect |
Jul 08, 2011 | Land Evidence Date |