Action Date | Action Description |
---|---|
Apr 14, 2011 | Assent Application Received |
Apr 18, 2011 | Administrative Review for Completeness |
Apr 19, 2011 | Team Review for Completeness |
Apr 19, 2011 | Team Review for Completeness |
Apr 19, 2011 | Application Accepted |
Apr 25, 2011 | Engineering Report |
May 02, 2011 | HPHC Historical Preservation No Effect |
May 09, 2011 | Additional Information Received |
May 10, 2011 | Biologist Report |
May 12, 2011 | Typist for Processing |
May 12, 2011 | Permit Approved |
May 17, 2011 | Executive Sign Off |
May 17, 2011 | Sent to Photo Copy |
Jun 14, 2011 | Land Evidence Date |
May 02, 2016 | Correspondence Received |