Action Date | Action Description |
---|---|
Engineering Report | |
Apr 25, 2011 | Maintenance Certification Request |
Apr 26, 2011 | Administrative Review for Completeness |
Apr 28, 2011 | Team Review for Completeness |
Apr 28, 2011 | Team Review for Completeness |
Apr 28, 2011 | Application Accepted |
May 16, 2011 | HPHC Historical Preservation No Effect |
Jun 06, 2011 | 30 day Public Notice Issued |
Jun 30, 2011 | Public Notice End Date Extension Granted |
Jul 06, 2011 | Public Notice End Date |
Jul 25, 2011 | US Army Corps of Engineers Approval Received |
Jul 27, 2011 | Dock/1.1.6 Review approval |
Aug 22, 2011 | Correspondence Received |
Sep 07, 2011 | Biologist Report |
Sep 09, 2011 | Category A* (Docks) |
Sep 09, 2011 | Land Evidence Date |
Sep 14, 2011 | Typist for Processing |
Sep 14, 2011 | Permit Approved |
Sep 15, 2011 | Executive Sign Off |
Sep 15, 2011 | Sent to Photo Copy |
Jan 26, 2012 | Commencement of Work Notice received |