Action Date | Action Description |
---|---|
Dec 12, 2011 | Assent Application Received |
Dec 13, 2011 | Administrative Review for Completeness |
Dec 21, 2011 | Team Review for Completeness |
Dec 21, 2011 | Team Review for Completeness |
Dec 21, 2011 | Application Accepted |
Dec 21, 2011 | Category B assigned |
Jan 03, 2012 | 30 day Public Notice Issued |
Jan 04, 2012 | HPHC Historical Preservation No Effect |
Jan 26, 2012 | Additional Information Received |
Jan 27, 2012 | Biologist Report |
Feb 03, 2012 | Public Notice End Date Extension Granted |
Feb 03, 2012 | Public Notice End Date |
Feb 07, 2012 | Engineering Report |
Feb 09, 2012 | Typist for Processing |
Feb 09, 2012 | Category A assigned |
Feb 09, 2012 | Permit Approved |
Feb 15, 2012 | Executive Sign Off |
Feb 15, 2012 | Sent to Photo Copy |
Feb 21, 2012 | Land Evidence Date |
Mar 06, 2012 | Correspondence Received |
Apr 02, 2012 | Water Quality Certification |
Apr 05, 2012 | Commencement of Work Notice received |
May 09, 2012 | Additional Information Received |
May 10, 2012 | Correspondence Mailed/Faxed/E-mailed |
Jan 23, 2013 | Correspondence Received |