Action Date | Action Description |
---|---|
Feb 29, 2012 | Assent Application Received |
Feb 29, 2012 | Administrative Review for Completeness |
Mar 06, 2012 | Team Review for Completeness |
Mar 06, 2012 | Team Review for Completeness |
Mar 06, 2012 | Application Accepted |
Mar 12, 2012 | Biologist Report |
Mar 12, 2012 | Engineering Report |
Mar 12, 2012 | Typist for Processing |
Mar 12, 2012 | Executive Sign Off |
Mar 12, 2012 | Sent to Photo Copy |
Mar 12, 2012 | Permit Approved |
Mar 22, 2012 | Land Evidence Date |
May 16, 2012 | HPHC Historical Preservation No Effect |