Action Date | Action Description |
---|---|
Ready to Schedule Semi-Monthly Meeting | |
May 15, 2012 | Assent Application Received |
May 17, 2012 | Administrative Review for Completeness |
Jun 25, 2012 | Team Review for Completeness |
Jun 25, 2012 | Team Review for Completeness |
Jun 25, 2012 | Application Accepted |
Jun 28, 2012 | Category B assigned |
Jul 11, 2012 | HPHC Historical Preservation No Effect |
Jul 26, 2012 | Additional Information Received |
Jul 27, 2012 | 30 day Public Notice Issued |
Aug 27, 2012 | Public Notice End Date |
Aug 27, 2012 | Objections/Comments Received |
Aug 31, 2012 | Public Notice End Date Extension Granted |
Sep 20, 2012 | Correspondence Received |
Oct 16, 2012 | Biologist Report |
Oct 17, 2012 | Engineering Report |
Oct 18, 2012 | Executive Signoff of Staff Reports |
Oct 24, 2012 | Ready to Schedule Semi-Monthly Meeting |
Oct 24, 2012 | Mail Agenda Notice |
Nov 09, 2012 | Correspondence Received |
Nov 13, 2012 | Semi-Monthly Meeting Date Scheduled |
Nov 28, 2012 | Continuance Requested |
Dec 03, 2012 | Mail Agenda Notice |
Dec 11, 2012 | Semi-Monthly Meeting Held |
Dec 11, 2012 | Continued Application by the Council |
Dec 11, 2012 | Semi-Monthly Meeting Date Scheduled |