Action Date | Action Description |
---|---|
Jul 31, 2012 | Assent Application Received |
Jul 31, 2012 | Administrative Review for Completeness |
Aug 03, 2012 | Team Review for Completeness |
Aug 03, 2012 | Application Accepted |
Aug 21, 2012 | HPHC Historical Preservation No Effect |
Sep 04, 2012 | Additional Information Received |
Nov 26, 2012 | 30 day Public Notice Issued |
Dec 26, 2012 | Public Notice End Date |
Jan 14, 2013 | US Army Corps of Engineers Approval Received |
Jan 16, 2013 | Biologist Report |
Jan 18, 2013 | Category B assigned |
Feb 04, 2013 | Typist for Processing |
Feb 05, 2013 | Executive Sign Off |
Feb 05, 2013 | Sent to Photo Copy |
Feb 13, 2013 | Assent Correction Mailed |
Feb 13, 2013 | Permit Approved |
Apr 03, 2013 | Land Evidence Date |
Apr 03, 2013 | Modification Request |
Apr 19, 2013 | HPHC Historical Preservation No Effect |
May 03, 2013 | Additional Information Received |
May 06, 2013 | Sent to Photo Copy |
May 20, 2013 | Permit Approved |
May 20, 2013 | Assent Amended |
May 20, 2013 | Typist for Processing |
May 21, 2013 | Executive Sign Off |
May 21, 2013 | Engineering Report |
Jun 11, 2013 | Land Evidence Date |