Action Date | Action Description |
---|---|
May 07, 2013 | Dredge Application |
May 07, 2013 | Administrative Review for Completeness |
May 09, 2013 | Team Review for Completeness |
May 09, 2013 | Application Accepted |
May 22, 2013 | Joint Public Notice |
May 22, 2013 | Category B assigned |
Jun 22, 2013 | Public Notice End Date |
Jun 25, 2013 | HPHC Historical Preservation No Effect |
Jul 17, 2013 | DEM Dredge Permit |
Jul 24, 2013 | Biologist Report |
Jul 24, 2013 | Dredge Report |
Jul 26, 2013 | Executive Signoff of Staff Reports |
Aug 05, 2013 | Mail Agenda Notice |
Aug 15, 2013 | US Army Corps of Engineers Approval Received |
Aug 27, 2013 | Semi-Monthly Meeting Postponed |
Aug 27, 2013 | Ready to Schedule Semi-Monthly Meeting |
Aug 27, 2013 | Mail Agenda Notice |
Aug 27, 2013 | Semi-Monthly Meeting Date Scheduled |
Sep 10, 2013 | Council Approval Granted |
Sep 10, 2013 | Semi-Monthly Meeting Date Scheduled |
Sep 10, 2013 | Semi-Monthly Meeting Held |
Sep 26, 2013 | 30 Day Appeal Notification to Owner |
Sep 26, 2013 | Legal Response/Decision |
Oct 02, 2013 | Dredge Permit Issued |
Oct 02, 2013 | Typist for Processing |
Oct 02, 2013 | Stipulation Package from Biologist |
Oct 02, 2013 | Stipulation Package by Engineer |
Oct 03, 2013 | Executive Sign Off |
Oct 03, 2013 | Sent to Photo Copy |
Jan 12, 2015 | Correspondence Mailed/Faxed/E-mailed |
Jan 15, 2015 | CAD Cell Fee Due-Final |