Action Date | Action Description |
---|---|
Aug 30, 2013 | Assent Application Received |
Sep 02, 2013 | Administrative Review for Completeness |
Sep 04, 2013 | Team Review for Completeness |
Sep 04, 2013 | Application Accepted |
Sep 27, 2013 | Additional Information Received |
Oct 18, 2013 | Additional Information Received |
Oct 28, 2013 | Permit Approved |
Oct 29, 2013 | Biologist Report |
Oct 29, 2013 | Engineering Report |
Oct 30, 2013 | Land Evidence Date |
Nov 19, 2013 | HPHC Historical Preservation Comments/Concerns |
Jan 07, 2014 | Plans Received |