Action Date | Action Description |
---|---|
HPHC Review Pending | |
Sep 17, 2013 | Assent Application Received |
Sep 17, 2013 | Administrative Review for Completeness |
Oct 01, 2013 | Team Review for Completeness |
Oct 01, 2013 | Application Accepted |
Oct 09, 2013 | HPHC Historical Preservation No Effect |
Nov 05, 2013 | 30 day Public Notice Issued |
Nov 25, 2013 | Correspondence Received |
Nov 26, 2013 | Public Notice End Date Extension Granted |
Dec 05, 2013 | Public Notice End Date |
Dec 23, 2013 | Correspondence Received |
Mar 03, 2014 | US Army Corps of Engineers Approval Received |
Mar 05, 2014 | Engineering Report |
Mar 10, 2014 | Typist for Processing |
Mar 10, 2014 | Permit Approved |
Mar 11, 2014 | Executive Sign Off |
Mar 11, 2014 | Sent to Photo Copy |
Apr 29, 2014 | Land Evidence Date |
Feb 15, 2019 | Modification Request |
Feb 18, 2019 | Administrative Review for Completeness |
Mar 15, 2019 | Deficient Application - Owner Notification Sent |
Sep 24, 2019 | Deficient Application Discarded/No deficiency Reponse |
Sep 24, 2019 | Team Review for Completeness |