Action Date | Action Description |
---|---|
Nov 22, 2013 | Assent Application Received |
Nov 25, 2013 | Administrative Review for Completeness |
Dec 16, 2013 | Correspondence Received |
Jan 22, 2014 | Additional Information Received |
Jan 22, 2014 | Application Accepted |
Jan 22, 2014 | Team Review for Completeness |
Feb 04, 2014 | 30 day Public Notice Issued |
Feb 20, 2014 | HPHC Historical Preservation No Effect |
Mar 04, 2014 | Public Notice End Date |
Mar 11, 2014 | Engineering Report |
Mar 14, 2014 | Typist for Processing |
Mar 14, 2014 | Permit Approved |
Mar 18, 2014 | Executive Sign Off |
Mar 18, 2014 | Sent to Photo Copy |
Apr 03, 2014 | Land Evidence Date |
Apr 09, 2014 | Additional Information Received |