Action Date | Action Description |
---|---|
Dec 19, 2013 | Assent Application Received |
Dec 20, 2013 | Administrative Review for Completeness |
Dec 24, 2013 | Team Review for Completeness |
Dec 24, 2013 | Application Accepted |
Jan 13, 2014 | HPHC Historical Preservation No Effect |
Feb 19, 2014 | Plans Received |
Feb 20, 2014 | Typist for Processing |
Feb 20, 2014 | Biologist Report |
Feb 20, 2014 | Permit Approved |
Feb 21, 2014 | Executive Sign Off |
Feb 21, 2014 | Sent to Photo Copy |
Mar 20, 2014 | Land Evidence Date |