Action Date | Action Description |
---|---|
Aug 04, 2014 | Assent Application Received |
Aug 04, 2014 | Administrative Review for Completeness |
Aug 08, 2014 | Team Review for Completeness |
Aug 08, 2014 | Application Accepted |
Aug 08, 2014 | Category B assigned |
Sep 04, 2014 | HPHC Historical Preservation No Effect |
Oct 01, 2014 | 30 day Public Notice Issued |
Oct 27, 2014 | Correspondence Received |
Nov 01, 2014 | Public Notice End Date |
Dec 17, 2014 | US Army Corps of Engineers Approval Received |
Dec 24, 2014 | Engineering Report |
Jan 15, 2015 | Mail Agenda Notice |
Jan 22, 2015 | Continued application |
Feb 03, 2015 | Ready to Schedule Semi-Monthly Meeting |
Feb 10, 2015 | Semi-Monthly Meeting Date Scheduled |
Feb 11, 2015 | Continued application |
Feb 23, 2015 | Correspondence Received |
Mar 13, 2015 | Ready to Schedule Semi-Monthly Meeting |
Mar 13, 2015 | Mail Agenda Notice |
Mar 16, 2015 | Correspondence Received |
Mar 24, 2015 | Council Approval Granted |
Mar 24, 2015 | Semi-Monthly Meeting Date Scheduled |
May 27, 2015 | 30 Day Appeal Notification to Owner |
May 27, 2015 | Legal Response/Decision |
May 29, 2015 | Stipulation Package by Engineer |
Jun 02, 2015 | Typist for Processing |
Jun 02, 2015 | Permit Approved |
Jun 04, 2015 | Executive Sign Off |
Jun 04, 2015 | Sent to Photo Copy |
Jun 08, 2015 | Land Evidence Date |
Oct 20, 2015 | Commencement of Work Notice received |