Action Date | Action Description |
---|---|
Aug 27, 2014 | Assent Application Received |
Aug 28, 2014 | Administrative Review for Completeness |
Sep 09, 2014 | HPHC Historical Preservation No Effect |
Sep 09, 2014 | HPHC Historical Preservation Comments/Concerns |
Oct 01, 2014 | Category B assigned |
Oct 01, 2014 | Application Accepted |
Oct 01, 2014 | Team Review for Completeness |
Oct 01, 2014 | 30 day Public Notice Issued |
Nov 01, 2014 | Public Notice End Date |
Dec 01, 2014 | Plans Received |
Dec 22, 2014 | Engineering Report |
Dec 23, 2014 | Supervisor Biologist SignOff |
Dec 24, 2014 | Supervisor Engineer SignOff |
Feb 25, 2015 | Ready to Schedule Semi-Monthly Meeting |
Feb 25, 2015 | Mail Agenda Notice |
Mar 09, 2015 | Objections/Comments Received |
Mar 10, 2015 | Council Approval Granted |
Mar 10, 2015 | Semi-Monthly Meeting Date Scheduled |
Mar 10, 2015 | Additional Information Received |
Mar 23, 2015 | Stipulation Package by Engineer |
Mar 24, 2015 | Legal Response/Decision |
Mar 26, 2015 | Typist for Processing |
Mar 26, 2015 | Permit Approved |
Mar 27, 2015 | Executive Sign Off |
Mar 27, 2015 | Sent to Photo Copy |