Action Date | Action Description |
---|---|
Jan 05, 2015 | Assent Application Received |
Jan 05, 2015 | Administrative Review for Completeness |
Jan 06, 2015 | Team Review for Completeness |
Jan 06, 2015 | Application Accepted |
Jan 20, 2015 | Entry of Appearance Received |
Jan 22, 2015 | Correspondence Received |
Jan 22, 2015 | Correspondence Received |
Jan 28, 2015 | 30 day Public Notice Issued |
Feb 02, 2015 | HPHC Historical Preservation No Effect |
Feb 28, 2015 | Public Notice End Date |
Mar 13, 2015 | Public Notice End Date Extension Granted |
Mar 16, 2015 | Correspondence Received |
Mar 19, 2015 | Objections/Comments Received |
Mar 20, 2015 | Engineering Report |
Mar 23, 2015 | Biologist Report |
Mar 26, 2015 | Permit Approved |
Mar 26, 2015 | Typist for Processing |
Mar 27, 2015 | Executive Sign Off |
Mar 27, 2015 | Sent to Photo Copy |
Mar 27, 2015 | Public Notice End Date Extension Granted |
Apr 13, 2015 | Land Evidence Date |