Action Date | Action Description |
---|---|
Sep 01, 2015 | Assent Application Received |
Sep 01, 2015 | Administrative Review for Completeness |
Sep 01, 2015 | Team Review for Completeness |
Sep 01, 2015 | Application Accepted |
Sep 24, 2015 | Additional Information Received |
Sep 29, 2015 | HPHC Historical Preservation Comments/Concerns |
Oct 01, 2015 | Additional Information Received |
Oct 02, 2015 | 30 day Public Notice Issued |
Oct 08, 2015 | Plans Received |
Oct 15, 2015 | Additional Information Received |
Oct 17, 2015 | Public Notice End Date |
Oct 21, 2015 | Biologist Report |
Oct 21, 2015 | Engineering Report |
Oct 26, 2015 | Plans Received |
Oct 28, 2015 | Typist for Processing |
Oct 29, 2015 | Executive Sign Off |
Oct 29, 2015 | Sent to Photo Copy |
Oct 29, 2015 | Permit Approved |
Dec 03, 2015 | Water Quality Certification |
Jan 11, 2016 | Land Evidence Date |
Apr 28, 2020 | Correspondence Mailed/Faxed/E-mailed |