Action Date | Action Description |
---|---|
Jan 29, 2016 | Assent Application Received |
Jan 29, 2016 | Administrative Review for Completeness |
Feb 02, 2016 | Team Review for Completeness |
Feb 02, 2016 | Application Accepted |
Feb 02, 2016 | Engineering Report |
Feb 25, 2016 | HPHC Historical Preservation No Effect |
Feb 26, 2016 | Typist for Processing |
Mar 01, 2016 | Executive Sign Off |
Mar 01, 2016 | Sent to Photo Copy |
Mar 01, 2016 | Permit Approved |
Mar 21, 2016 | Land Evidence Date |