Action Date | Action Description |
---|---|
Feb 04, 2016 | Assent Application Received |
Feb 04, 2016 | Administrative Review for Completeness |
Feb 05, 2016 | Team Review for Completeness |
Feb 05, 2016 | Application Accepted |
Feb 18, 2016 | HPHC Historical Preservation No Effect |
Feb 29, 2016 | Plans Received |
Mar 01, 2016 | Biologist Report |
Mar 03, 2016 | Typist for Processing |
Mar 03, 2016 | Executive Sign Off |
Mar 03, 2016 | Sent to Photo Copy |
Mar 03, 2016 | Permit Approved |
Mar 09, 2016 | Land Evidence Date |