Action Date | Action Description |
---|---|
Mar 31, 2016 | Assent Application Received |
Apr 01, 2016 | Administrative Review for Completeness |
Apr 01, 2016 | Team Review for Completeness |
Apr 01, 2016 | Application Accepted |
Apr 20, 2016 | Additional Information Received |
May 03, 2016 | HPHC Historical Preservation No Effect |
May 11, 2016 | Plans Received |
May 19, 2016 | Typist for Processing |
May 20, 2016 | Executive Sign Off |
May 20, 2016 | Sent to Photo Copy |
May 20, 2016 | Biologist Report |
May 20, 2016 | Permit Approved |
Jun 07, 2016 | Land Evidence Date |