Action Date | Action Description |
---|---|
Oct 24, 2016 | Dredge Application |
Oct 26, 2016 | Administrative Review for Completeness |
Oct 26, 2016 | Joint Public Notice |
Oct 26, 2016 | Team Review for Completeness |
Oct 26, 2016 | Application Accepted |
Nov 10, 2016 | HPHC Historical Preservation No Effect |
Nov 28, 2016 | Public Notice End Date |
Dec 09, 2016 | Dredge Report |
Dec 09, 2016 | DEM Dredge Permit |
Dec 09, 2016 | Permit Approved |
Dec 15, 2016 | US Army Corps of Engineers Approval Received |
Feb 10, 2017 | Additional Information Requested from Applicant |
Feb 27, 2017 | CAD Cell Fee Due-Final |
Mar 27, 2017 | Duplicate Original Assent requested/mailed |
Apr 05, 2017 | Land Evidence Date |
Jul 20, 2017 | Plans Received |
Feb 18, 2020 | Plans Received |
Apr 17, 2020 | CAD Cell Fee Due-Final |
Dec 06, 2021 | Maintenance/Repair/Location within the Marina Perimeter |
Mar 22, 2022 | CAD Cell Fee Due - initial (letter) |
Mar 22, 2022 | CAD Cell Fee (initial) received |
Mar 22, 2022 | CAD Cell Fee Due-Final |