Action Date | Action Description |
---|---|
Oct 25, 2016 | Assent Application Received |
Oct 26, 2016 | Administrative Review for Completeness |
Oct 27, 2016 | Team Review for Completeness |
Oct 27, 2016 | Application Accepted |
Nov 09, 2016 | 30 day Public Notice Issued |
Nov 10, 2016 | HPHC Historical Preservation No Effect |
Dec 09, 2016 | Public Notice End Date |
Dec 21, 2016 | Public Notice End Date Extension Granted |
Aug 11, 2017 | Plans Received |
Sep 25, 2017 | Dock Meeting -- Approval |
Oct 06, 2017 | US Army Corps of Engineers Approval Received |
Oct 31, 2017 | Biologist Report |
Nov 01, 2017 | Typist for Processing |
Nov 01, 2017 | Executive Sign Off |
Nov 01, 2017 | Sent to Photo Copy |
Nov 01, 2017 | Permit Approved |
Nov 16, 2017 | Land Evidence Date |