Action Date | Action Description |
---|---|
Dec 02, 2016 | Assent Application Received |
Dec 02, 2016 | Administrative Review for Completeness |
Dec 13, 2016 | Team Review for Completeness |
Dec 13, 2016 | Deficient Application - Owner Notification Sent |
Jan 11, 2017 | Deficiency Response Received |
Jan 17, 2017 | Team Review for Completeness |
Jan 17, 2017 | Application Accepted |
Jan 27, 2017 | HPHC Historical Preservation No Effect |
Feb 10, 2017 | 30 day Public Notice Issued |
Mar 10, 2017 | Public Notice End Date |
Mar 20, 2017 | Public Notice End Date Extension Granted |
Mar 20, 2017 | US Army Corps of Engineers Approval Received |
Mar 20, 2017 | Dock/1.1.6 Review approval |
Mar 27, 2017 | Typist for Processing |
Mar 27, 2017 | Permit Approved |
Mar 27, 2017 | Biologist Report |
Mar 28, 2017 | Executive Sign Off |
Mar 28, 2017 | Category A* (Docks) |
Apr 10, 2017 | Land Evidence Date |
May 15, 2017 | Correspondence Received |
Mar 30, 2020 | Modification Request |
Mar 30, 2020 | Administrative Review for Completeness |
Apr 01, 2020 | Bio Team Review for Completeness |
Apr 01, 2020 | Deficient Application - Owner Notification Sent |
Nov 06, 2020 | Modification Request |
Nov 09, 2020 | Administrative Review for Completeness |
Nov 10, 2020 | Bio Team Review for Completeness |
Nov 10, 2020 | Project Manager |
Nov 10, 2020 | Application Accepted |
Nov 17, 2020 | 30 day Public Notice Issued |
Nov 20, 2020 | US Army Corps of Engineers Approval Received |
Nov 25, 2020 | HPHC Historical Preservation No Effect |
Nov 25, 2020 | HPHC Review Pending |
Dec 16, 2020 | Objections/Comments Received |
Dec 17, 2020 | Additional Information Received |
Dec 17, 2020 | Public Notice End Date |
Dec 31, 2020 | Plans Received |
Feb 08, 2021 | Application Cancelled |
Feb 08, 2021 | Biologist Report |