Action Date | Action Description |
---|---|
Dec 22, 2016 | Assent Application Received |
Dec 22, 2016 | Administrative Review for Completeness |
Jan 17, 2017 | Team Review for Completeness |
Jan 17, 2017 | Application Accepted |
Jan 26, 2017 | Biologist Report |
Jan 27, 2017 | Engineering Report |
Jan 30, 2017 | Typist for Processing |
Jan 30, 2017 | Executive Sign Off |
Jan 30, 2017 | Sent to Photo Copy |
Jan 30, 2017 | Permit Approved |
Feb 01, 2017 | Land Evidence Date |
Feb 03, 2017 | HPHC Historical Preservation No Effect |