Action Date | Action Description |
---|---|
Jan 04, 2017 | Assent Application Received |
Jan 05, 2017 | Administrative Review for Completeness |
Jan 06, 2017 | Team Review for Completeness |
Jan 06, 2017 | Team Review for Completeness |
Jan 06, 2017 | Application Accepted |
Jan 16, 2017 | Biologist Report |
Jan 16, 2017 | Engineering Report |
Jan 18, 2017 | Typist for Processing |
Jan 18, 2017 | Executive Sign Off |
Jan 18, 2017 | Sent to Photo Copy |
Jan 18, 2017 | Permit Approved |
Jan 27, 2017 | HPHC Historical Preservation No Effect |